JNV / Khurda / Phase - "A"
|
|
Cost As Per revised A / A & E/S 860.31 Lacs
|
|
Cost As Per Final Bill (Tentative) Excluding Contingency & C/A Charges 852.77 Lacs
|
|
Date of Commencement 18/01/2008
|
|
Date of Handing Over 01/10/2009
|
|
Sl. No.
|
Name of building
|
|
Plinth Area
|
Actual cost in Lacs
|
|
|
1
|
School Building
|
|
1913 Sqm
|
226.2
|
|
|
2
|
Boys Dorm with WR - 4 Nos.
|
|
1603 Sqm
|
189.55
|
|
|
3
|
Girls Dorm with WR - 2 Nos.
|
|
802 Sqm
|
94.77
|
|
|
4
|
Kitchen / Dining
|
|
757 Sqm
|
89.51
|
|
|
5
|
Staff Qr. T - V (1 No.)
|
8×60 Sqm
|
106 Sqm
|
12.53
|
|
|
6
|
Staff Qr. T - III (8 No.)
|
8×50 Sqm
|
480 Sqm
|
56.75
|
|
|
7
|
Staff Qr. T - II (4 No.)
|
8×40 Sqm
|
200 Sqm
|
23.64
|
|
|
8
|
Staff Qr. T - I (4 No.)
|
|
160 Sqm
|
18.92
|
|
|
9
|
Electric Sub Station
|
|
40 Sqm
|
4.73
|
|
|
10
|
Pump House
|
|
7.0 Sqm (Appx.
|
0.95
|
|
|
11
|
OHT1.00 lasc Liter
|
|
|
20
|
|
|
12
|
UGT1.00 lasc Liter
|
|
|
5.35
|
|
|
13
|
D.G.SET 25 KVA
|
|
|
4.00
|
|
|
|
Total Including External & Internal Electrification Complete.
|
|
|
746.9
|
|
|
14
|
CC Roads
|
|
|
|
|
|
|
3.50 M Wide
|
|
330.0 Mts
|
|
|
|
|
3.00 M Wide
|
|
277.0 Mts
|
|
|
|
|
7.00 M Wide (K / D)
|
|
08.0 Mts
|
|
|
|
|
5.40 M Wide (Front of SB)
|
|
23.60 Mts
|
|
|
|
|
6.60 M Wide (Front of SB)
|
|
06.65 Mts
|
|
|
|
|
4.30 M Wide (Front of SB)
|
|
10.3 Mts
|
|
|
|
15
|
Foot Path
|
|
|
|
|
|
|
1.50 M Wide
|
|
391.0 Mts
|
|
|
|
|
1.20 M Wide
|
|
118.70 Mts
|
|
|
|
|
2.30 M Wide T - I
|
|
3.70 Mts
|
|
|
|
|
2.45 M Wide T - II
|
|
2.45 Mts
|
|
|
|
|
Total cost of Development Work including Roads, Foot paths, drainage, Sewerage, Septic tank, Soak Pits sentry Room & Boundary wall
|
|
|
105.87
|
|
|
|
Total Cost of Project (Tentative as the final Bill is still under Checking)
|
|
|
852.77
|
|